Proposed Case for : 2019-AGL-17106-OE

faa.gov Tools: Printer graphicPrint this page
For information only.
This proposal has not yet been studied. Study outcomes will be posted at a later date.
Public comments are not requested, and will not be considered at this time.

Overview
Study (ASN): 2019-AGL-17106-OE
Prior Study:
Status: Work In Progress

   
Received Date: 10/02/2019
Entered Date: 10/02/2019
Map: View Map
Construction Info     Structure Summary
Notice Of: CONSTR
Duration: TEMP    (Months: 18    Days: 0)
Work Schedule: 02/01/2020  to  05/24/2022
   
   
Structure Type: Crane
Structure Name: TCF Bank Tower Temporary Crane
FCC Number:
   
Structure Details     Height and Elevation
Latitude (NAD 83): 42° 20' 13.87" N
Longitude (NAD 83): 83° 03' 06.73" W
Datum: NAD 83
City: Detroit
State: MI
Nearest County: Wayne
   
 
Proposed
Site Elevation:
603
Structure Height:
460
Total Height (AMSL):
1063

Frequencies
Low Freq High Freq Unit ERP Unit