Owner of Structure: |
Partners Healthcare Systems, Inc. |
|
|
|
|
Latitude: |
42° 23' 29.19" N |
Longitude: |
71° 04' 44.85" W |
Horizontal Datum: |
NAD 83 |
Site Elevation (SE): |
13 (nearest foot) |
Structure Height (AGL): |
218 (nearest foot) |
Site Elevation Determined By: |
Actual Pre-Built Survey |
|
|
Address: |
|
Address 2: |
|
City: |
Somerville |
State: |
MA |
|
|
|
|
Construction
Start Date: |
|
Estimated End
Date: |
|
Greatest Height Reached
Date: |
01/15/2016 |
|
|
Abandon Date: |
|
Dismantled Date: |
|
M&L Change Date: |
|
Extension Request Date: |
|
|
|
|
|
|
|
FCC Permit
Applied Date: |
|
FCC Permit Issued
Date |
|
|
|
|
|
Marking and Lighting: |
Red lights |
Estimated Date ADLS will be installed: |
|
Estimated Date ADLS will be operational: |
|
Date ADLS enabled: |
|
Date ADLS discontinued: |
|
|
|
|
|
Latest Supplemental Case Note: |
|
Comments: |
The required hazard avoidance lighting has been installed but not yet operational. The lighting is scheduled to be operational on or before May 2, 2016. |
|
|
|
|